Format "done" tasks style to eliminate crossout?
-
- Posts: 56
- Joined: Sat Jan 30, 2010 1:14 am
Format "done" tasks style to eliminate crossout?
As you know, when we click the completed checkbox on a task, the default format automatically crosses out the title. I want to change this so the title is not crossed out, but so far I haven't been able to find a way to do this. Am I missing something? (Probably)
yep, you have
Go to "Tools / Options"
Select "Tasks & Reminders"
Unselect "Strikeout completed tasks"
Is that what you want ?
Go to "Tools / Options"
Select "Tasks & Reminders"
Unselect "Strikeout completed tasks"
Is that what you want ?
-
- Posts: 56
- Joined: Sat Jan 30, 2010 1:14 am
I was looking for it under Format/Styles. Sigh. Thanks.mfelix wrote:yep, you have
Go to "Tools / Options"
Select "Tasks & Reminders"
Unselect "Strikeout completed tasks"